June 2011

Re-grind and CIL area completed

CIL area tank top steel

SAG mill and CIL reagent mixing area

SAG mill feed chute ready for rolling into position

Power factor capacitors for treatment plant power

Final trim underway to earthworks between float and CIL

Stockpile area basement fill being installed

Process water pond embankment nearly full with water

Cyanide tailings storage membrane lining