Re-grind and CIL area completed
.jpg)
CIL area tank top steel
SAG mill and CIL reagent mixing area
SAG mill feed chute ready for rolling into position
Power factor capacitors for treatment plant power
Final trim underway to earthworks between float and CIL
Stockpile area basement fill being installed
Process water pond embankment nearly full with water
Cyanide tailings storage membrane lining